Auditor-General: Putrajaya risked lives in delaying Bukit Jalil stadium roof repair


By Debra Chong, The Malaysian Insider

KUALA LUMPUR, Oct 24 — Putrajaya risked public safety when it took four years to approve funds to repair the damaged roof at the Bukit Jalil National Stadium, the Auditor-General said in his report released today.

The report highlighted that the Merdeka Stadium Corporation (MSC), a federal statutory body responsible for the management of all national sports complexes, had applied to repair damage to the Bukit Jalil Stadium a total of four times since 2006.

The government finally approved RM30 million to repair the damaged stadium (picture) in December last year, the report added.

“The Auditor is of the view the delay in completing the roof repairs at Bukit Jalil National Stadium… was because the government did not approve the allocation applied for since 2006.

“This could jeopardise the comfort of users who would be exposed to the rain and endanger their safety if the roof collapsed especially for international events,” the report said.

The report said the 90,000-capacity stadium had a 10-year warranty for the German-made membrane roof cover, which expired in 2008, but noted MSC could not get a replacement roof because it was damaged by fireworks.

It noted too the stadium, which has hosted 2,100 events between 2008 and 2010, require other immediate repairs and pointed out rusty and loose cable screws holding up the roof.